One of the last projects in winter condition is behind us. We used three different types of plates at our telecommunications mast construction site in Rokitno. The kind of plates depended on the field condition.
The Strong plates stayed installed in the local depression of the terrain, where the conditions were the worst, Steel plates in the place of limited assembly space but with access allowance for property owners. Whereas Plates Metrum5 were installed on the remaining part of the farmland through which access was possible.
The completed road was used throughout the whole construction period for access of assembly
teams as well as excavators, and trucks with a concrete crane to crane lift with a capacity of 130 tons