The First Truck at the Stadium

Rampa - Tarczyński Arena Wrocław
For the first time in history, a truck and crane have entered the field of Tarczyński Arena. See how Alu Deck plates enabled the construction of a temporary ramp.

Temporary ramp at Tarczyński Arena Stadium – first entry of a truck and crane onto the stadium field

For the first time in history, Tarczyński Arena Stadium in Wrocław witnessed the entry of a truck with a trailer and a mobile crane onto its field. This was made possible by an innovative solution in the form of a temporary ramp that we designed and built last year.

Our goal was to create a safe and durable structure that would allow heavy equipment to enter without risking damage to the stadium’s surface. After a series of tests and optimizations, we implemented a system enabling the passage of full-size trucks and cranes, significantly expanding the organizational capabilities of the stadium. This solution, among other things, will allow for the preparation of infrastructure for the Dawid Podsiadło concert, which will take place in June 2024.

Technical challenges and the need for a ramp

Football stadiums are not adapted for the movement of heavy vehicles, so implementing this solution required careful planning and testing. The key challenges that needed to be addressed included:

  • Protection of the stadium field – it was necessary to use a system that evenly distributed the pressure of vehicles and prevented surface damage.
  • Safe entry for heavy equipment – the ramp had to withstand the pressure generated by the mobile crane and full-size trucks while ensuring adequate stability.
  • Quick assembly and disassembly – the structure had to be easy to install and remove after the event to avoid disrupting the schedule of other events.
  • Compliance with stadium standards – the solution had to meet the technical requirements of the facility and not interfere with its permanent infrastructure.

To meet these requirements, we decided to use Alu Deck aluminum plates, which are perfect for such projects.

Alu Deck aluminum plates

The primary element of the ramp’s construction was Alu Deck aluminum plates, which provided the necessary strength while being lightweight and easy to assemble. Their use allowed for the creation of a stable surface enabling the safe entry of heavy equipment onto the stadium field.

Key advantages of using Alu Deck plates:

  • high load capacity, allowing the passage of trucks and cranes,
  • anti-slip surface, increasing vehicle movement safety,
  • resistance to variable weather conditions, which is important for outdoor events,
  • modular construction, allowing for quick ramp assembly and disassembly.

Check out our other road plates and choose the best solution tailored to your investment.

Implementation effects – what benefits did the temporary ramp provide?

Thanks to the implementation of this innovative solution, it became possible to:

  • introduce heavy equipment onto the stadium field, opening up new organizational possibilities,
  • protect the stadium surface, through even pressure distribution,
  • increase the potential of Tarczyński Arena as a multifunctional facility,
  • prepare infrastructure for large events, including concerts and mass events,
  • flexibly adapt the stadium space to various logistical needs.

Summary – why use Alu Deck aluminum plates?

Temporary solutions, like the ramp made of Alu Deck plates, allow for a safe and quick drive onto the stadium field, significantly increasing the facility’s functionality. Thanks to their durability, lightness, and modular construction, these plates can be used in both sports event organization and concerts, ensuring surface protection and user safety.

If your investment requires road plate rental, contact us. We offer aluminum, steel, and wooden plates, tailored to various operational conditions. Feel free to contact us.

Contact us

Other projects

Warsaw Jumping - wykorzystanie płyt aluminiowych Alu Deck HD

Warsaw Jumping

Płyty drogowe na wynajem – skuteczna ochrona podłoża na Warsaw Jumping 2024 Warsaw Jumping to prestiżowe wydarzenie jeździeckie, które co roku przyciąga najlepszych zawodników i entuzjastów sportów konnych. Organizacja takiego

Read More »

Modern Construction

Nowoczesne budownictwo wymaga nowoczesnych, ale też prostych i sprawdzonych rozwiązań. Nasze rozwiązania sprawdziły się przy kolejnym już domu modułowym tym razem w Warszawie. Na potrzeby montażu platformę roboczą dla ciężkiego

Read More »
Linia 400kV Kozienice-Miłosna

400 kV line Kozienice-Miłosna

The construction of the 400 kV Kozienice-Miłosna line required 60 km of temporary roads and platforms for heavy equipment. Thanks to Metrum and Strong plates, transportation and assembly went smoothly. Check out the solutions that were applied!

Read More »
×

Lait Content Creator