Road for Oversized Vehicles in the Gostynin Area

Tymczasowa droga dojazdowa pod pojazd ponadgabarytowy w rejonie Gostynina - Płyty STRONG
We lifted and leveled a road section in Gostynin, ensuring safe passage for oversized transports with Metrum plates.

Alignment of the Municipal Road Slope in the Gostynin Region – Safe Transport of Wind Power Plant Components

In the new year, we continue to showcase the unusual applications of our panels. Each project has its unique challenges that require the use of appropriate technologies. This time, our task was aligning the slope of a municipal road in the Gostynin region to enable the safe passage of oversized transports with wind power plant components.

Logistical Challenges and Technology Selection

Local roads are often not adapted to handle heavy and oversized transports. In this case, the key challenge was raising and leveling a section of the road to ensure stability and safe passage for vehicles transporting wind power plant structural components. The requirements included:
  • Raising the road surface by 20 cm over a section of approximately 120 meters.
  • Using a stable and temporary surface that does not affect the durability of the existing road infrastructure.
  • Quick assembly and disassembly – the entire operation had to take place just before the passage and be completed immediately after the delivery of the components.

Metrum Wooden Road Plates – The Ideal Solution for Temporary Roads

To meet the project requirements, we used Metrum wooden road plates, which are perfect for such conditions. Laid in two layers in a bidirectional arrangement, they allowed for effective raising of the road surface and ensuring its adequate load-bearing capacity. Their key advantages are:
  • Stability and durability – these plates effectively transfer large loads, which was crucial for oversized transport.
  • Ease of assembly and disassembly – allowed for rapid road adaptation before the passage and restoration to its original state right after the transport ended.
  • Excellent grip – prevented slipping and increased vehicle safety.
  • Eco-friendly solution – wood is a natural material that does not negatively impact the environment and can be reused.

Efficient Execution and Timely Deliveries

Thanks to the use of Metrum plates, we successfully raised and leveled the road surface, allowing for the smooth delivery of all wind power plant components on time. After the passage of oversized transports, the plates were immediately removed, and the road was restored to its original state.

Take Advantage of Road Plate Rentals

Planning a similar project and need temporary roads on challenging terrain? We offer road plate rentals that will perform well in tough conditions and ensure transport safety. Contact us – we will help you choose the best solution for your project!

Contact us

Other projects

Master Truck Nowa Wieś

Master Truck Poland New Village

During the Master Truck Show 2023, we used Alu Deck HD Panels to create a two-lane temporary road at the airport in Polska Nowa Wieś. This allowed hundreds of trucks to move safely and ensured the airport’s surface was protected. See how our solutions support major automotive events!

Read More »
Linia 400kV Kozienice-Miłosna

400 kV line Kozienice-Miłosna

The construction of the 400 kV Kozienice-Miłosna line required 60 km of temporary roads and platforms for heavy equipment. Thanks to Metrum and Strong plates, transportation and assembly went smoothly. Check out the solutions that were applied!

Read More »
Droga dojazdowa do farmy fotowoltaicznej

Access Road in the Lubusz Voivodeship

The construction of a photovoltaic farm in the Lubusz Voivodeship required an access road for transformer transport. Thanks to the rented wooden Metrum plates, the delivery was smooth and safe. Check out the solutions that were applied!

Read More »
Masz telekomunikacyjny Ociesęki

Telecommunication Mast Ociesęki

The installation of a telecommunications mast in Ociesęki required an access road on a steep slope. Thanks to Alu Deck HD plates, the crane entered without any problems, and the work was completed in one day.

Read More »
×

Lait Content Creator